Brick and tile factory

Project description

The construction of a new brick and tile plant, mining limestone, mining of clay.

Project summary

Project: construction of a new brick factory.

The relevance of the data: September 2018

Planned plant capacity: 30 million pieces per year, of which 25 million units – facial hollow; 5 million units– facial solid.

Start date of production: may 2019 plan 2020 for the calculations.

Planning period: 6 years; 2018-2024. inclusive.

The initial investment for the project (without VAT): 600 million rubles.

Total revenue in the planning period (without VAT): 2, 25 billion rubles

Balance profit for the period: 383, 3 million.

Net profit for the period: 291 million.

The amount of accumulated depreciation: 600 million rubles.

Reserve additional savings: 48, 5 million.

The overall profitability of the project: 13%.

The payback period of the project: 2024

Net present current value: 123, 24 million rubles.

Discount rate: 14%.

Project detailed information is available to investors after authorization.

Project detailed information is available to investors after authorization.

Translated by "Yandex.Translator"
Project No. 48168
Created on: 01.04.2019

Russia, Crimea Republic, the village Soviet


Project price: 600 000 000

Investments volume: 600 000 000


Stage: Idea


623 reviews

Contact details of entrepreneur

Legeza Igor Adeksandrovich

Russia, Crimea Republic, the village Soviet
Industry, Mining industry, Construction